Hello Everyone, I know this post comes a few days late but because of the short holiday work week I decided to hold off last weeks post and combine it with this short weeks post. Anyways Thanksgiving is tomorrow and I cant wait to get some of moms homemade cooking in me, I can already smell the turkey in oven.
Anyways at Levy I have been super busy, John and I went out to the landfill twice last week to survey elevations, this was a very tough and very cold experience. Before going to the landfill wasn't that bad but add sub 35degree, 30mph wind to the equation everything comes a bit more difficult. So the next time you see a surveying crew just know that the job isn't as easy as it may seem. Also last week I completed work on the 612 conveyor drawing and sent that over to John for approval. The main project I involved myself with last week was the CMS copper plant walkway, Getting this correct and safe are the key focal points of my proposal.
Now onto this short week, one of the main projects going on right now is Wallace Stone Jaw Crusher Replacement. This last week as been filled with computer aided drafting. I have been generating 3D models of the structure, crusher, and many other components. This will be to give others a better grasp of what the changes will be. The 3D generations will be a assets in the construction faze as well. So the better part of 3 days has been dedicated to this project.
Over the last week and a half I have used not only my knowledge in CAD, but also my practical experience from many past group projects that you attain through different ME classes. Keeping it simple is how I would best describe at how I approached the last week and half. On another note, Levy's office atmosphere has really picked up around the holiday's which has a nice feel to it.
By the way my Spartans are going to the Big Ten Championship Game as winners of the Legends Division, I cant wait to watch them win it all in Indianapolis. Happy Thanksgiving everyone!!!!!!!! Go Lions